Murunkan – Mannar Water Supply Scheme II

  • Date: February 2013
  • Client: National Water Supply and Drainage Board
  • Project Type: Pipe Supply and Laying

More Information

  • Contract Name:  Dry Zone Urban Water & Sanitation Project, Supply & Laying of DI, HDPE, PVC pipes, specials, fittings & valves for transmission main & distribution system in Mannar Water Supply
  • Contract Start: February 2013
  • Client: National Water Supply and Drainage Board
  • Project Scope:
    • HDPE (Dia 315 – 355mm) – 5.87Km
    • UPVC (Dia 63 – 225mm) – 204 Km
  • ADB funded – PIPES/M/11

     

Start Point of Construction

Murunkan – Start point of construction

End Point of Construction

Mannar – End point of construction